Skip to content

 The Federal Law That Requires Bonding on Government Construction Projects

If you're a contractor who wants to bid on federal construction work, the Miller Act is the law you need to understand. It's the reason performance and payment bonds are required on virtually every federal construction contract - and it's been shaping how the government manages construction risk since 1935.

The Miller Act isn't complicated, but the details matter. Knowing what it requires, who it protects, and how it affects your ability to bid and win federal work is fundamental to competing in public construction. This page covers the law in plain English - what it says, how it's applied, and what it means for contractors at every level.

 What Is the Miller Act?

The Miller Act is a federal statute, codified at 40 U.S.C. §§ 3131–3134 , that requires contractors on federal construction projects to furnish both a performance bond and a payment bond before the contract is awarded. Originally enacted in 1935 to replace the earlier Heard Act of 1894, it was recodified in 2002 but its core requirements have remained consistent for nearly a century.

The statute itself sets the bonding threshold at contracts exceeding $100,000. However, the Federal Acquisition Regulation (FAR), which implements the Miller Act's requirements in practice, sets the bonding threshold at $150,000 for construction contracts. For contracts between $35,000 and $150,000, the FAR provides alternative forms of payment protection instead of a full payment bond. For contracts over $150,000, both a performance bond and a payment bond are mandatory.

In practical terms: if you want to bid on any federal construction contract worth more than $150,000, you must be able to provide performance and payment bonds. No bond, no bid.

Before you can win that contract, you typically submit a bid bond with your proposal, then provide the performance and payment bonds once the job is awarded.

 Why Does the Miller Act Exist?

The Miller Act addresses two problems that are unique to government construction.

First, the government needs assurance that contractors will complete the work. When a contractor abandons a federal project or fails to perform, it doesn't just create a financial loss - it delays critical public infrastructure, disrupts services, and wastes taxpayer dollars. The performance bond guarantees that if the contractor defaults, the surety will step in to ensure the project gets finished.

Second, subcontractors and material suppliers need a way to get paid. On private construction projects, unpaid subs and suppliers can file mechanics' liens against the project property to secure their payment. But on federal projects, you can't file a lien against government property - sovereign immunity prevents it. Without the Miller Act, subcontractors working on federal jobs would have no practical recourse if the general contractor failed to pay them. The payment bond fills that gap by giving them a direct claim against the surety.

The U.S. Small Business Administration recognizes the importance of this framework and operates a Surety Bond Guarantee Program specifically to help small contractors who might otherwise struggle to obtain the bonds required under the Miller Act.

.

 What Bonds Does the Miller Act Require?

The Miller Act requires two bonds on qualifying federal construction contracts: a performance bond and a payment bond.

The performance bond protects the federal government. It guarantees that the contractor will complete the project in accordance with the terms of the contract. If the contractor defaults, the surety is obligated to resolve the situation - typically by financing a replacement contractor, providing financial assistance to the original contractor, or compensating the government for its losses. The performance bond amount is set by the contracting officer at a level they consider adequate to protect the government's interest, which in practice usually means 100% of the contract value.

The payment bond protects subcontractors, laborers, and material suppliers. It guarantees that the contractor will pay all downstream parties who provide labor and materials on the project. The payment bond amount must equal the total contract value unless the contracting officer determines that a bond in that amount is impractical, in which case they can set a different amount - but it can never be less than the performance bond amount.

Both bonds must be furnished before the contract is awarded and become binding when the contract is signed. They must be issued by a surety satisfactory to the contracting officer, which in practice means a surety company listed on the U.S. Department of the Treasury's Circular 570   - the official list of approved sureties for federal bonds.

 Learn more about Performance Bonds

 Learn more about Payment Bonds 

 Who Does the Miller Act Apply To?

The Miller Act applies to prime contractors - the contractors who enter into a direct contract with the federal government. If you're awarded a federal construction contract over $150,000, you're the one who must furnish the bonds.

Subcontractors are not required to provide Miller Act bonds to the government. However, many general contractors require their subcontractors to carry bonds as a condition of the subcontract, particularly on larger or more complex projects. This is a contractual requirement, not a Miller Act requirement - but it operates on the same principle. The GC wants the same assurance from their subs that the government wants from the GC.

The Miller Act covers contracts for the construction, alteration, or repair of any public building or public work of the federal government. This includes new construction, renovation, infrastructure work, facility maintenance, and any other project that involves physical work on government property or public works. It does not apply to supply contracts, service contracts, or contracts that don't involve construction.

Bidding federal work takes more than a low number.

Miller Act bonds come from a surety relationship built before bid day. Our bond team builds the program behind the bond - financial presentation, capacity, and the underwriting file - so you can bid federal projects with confidence.

Request a Bond Program Review

Questions about Miller Act requirements? Call the Grit bond team at (801) 505-5500.

 Payment Bond Claim Rights Under the Miller Act

One of the most important practical aspects of the Miller Act for the construction industry is the payment bond claim process. If you're a subcontractor or supplier working on a bonded federal project and you haven't been paid, the Miller Act gives you a specific legal path to recover your money.

It also gives you a clock. Miss it and the claim is gone, no matter how right you are about the money.

The two 90-day rules that get confused

There are two separate 90-day rules in the Miller Act, they do different jobs, and contractors mix them up constantly.

The 90-day waiting period applies to everyone. No claimant can file suit until 90 days have passed since the last day they furnished labor or materials. That window exists to give the prime contractor and the surety a chance to settle up before anyone goes to court.

The 90-day notice requirement applies only to second-tier claimants. If you contracted with a subcontractor rather than with the prime, you must give the prime contractor written notice of your claim within 90 days of your last day of work or delivery. The notice needs to state the amount claimed and name the party you contracted with.

Two details decide cases here. The notice must actually be received by the prime inside the 90 days, not simply mailed on day 89 (Pepperburn's Insulation, Inc. v. Artco Corp., 970 F.2d 1340, 4th Cir. 1992). And for a second-tier claimant the notice is a condition precedent, which is the legal way of saying no notice, no claim, regardless of the merits.

First-tier claimants who contract directly with the prime do not have to send that notice. Send one anyway. It often gets the invoice paid without a lawsuit, and if it doesn't, it shows the court you tried.

Who is actually covered

Miller Act payment bond protection reaches the first and second tiers only. If you have a direct contract with the prime, you're covered. If you have a contract with a first-tier subcontractor, you're covered.

Below that, the protection stops. A supplier to a second-tier subcontractor has no Miller Act claim, and neither does a sub-subcontractor further down the chain. Suppliers to suppliers are not protected either. Perfect notice does not fix a tier problem.

This is worth knowing before you sign, not after you're unpaid. If you're taking work three levels down on a federal job, the payment bond is not standing behind you, and you should be pricing and securing that risk some other way.

The one-year deadline, and what does not extend it

Every Miller Act payment bond claim must be filed in federal court within one year of the last day the claimant performed work or supplied materials. Combined with the 90-day waiting period, that leaves a practical nine-month window to file.

Going back to the site to do repair or warranty work does not restart that clock. Neither does a punch list item or a courtesy fix. The date that counts is the last day of your original contract work, which is frequently earlier than contractors assume.

Keep dated delivery tickets and daily logs on every federal job. When a payment fight starts eight months later, that paperwork is what establishes your last-furnishing date, and the date is the whole case.

 Learn more about how Payment Bond claims work

 Little Miller Acts - State and Local Bonding Requirements

The Miller Act applies only to federal construction projects. But its framework was so effective that virtually every state has enacted its own version, commonly called a "Little Miller Act," imposing similar bonding requirements on state and local government construction projects.

If you bid public work for a state, a county, a city, a school district, or a water district, you are working under a Little Miller Act, not the federal one.

What changes from state to state

Four things move: the contract dollar threshold that triggers bonding, which bonds are required and in what amount, the notice procedure for making a claim, and the deadline to file suit. A contractor who assumes the federal rules carry over to a state job is the contractor who misses a notice deadline.

Why the dollar threshold you found online is probably wrong

Most bonding charts print one dollar figure per state. That single number is the most common error in public construction bonding, because in a lot of states the figure in the statute is not a bond trigger at all. It turns out to be one of four other things.

A waiver ceiling. Washington, South Carolina and Mississippi all require bonds with no dollar floor and then allow an exemption underneath a figure. Washington lets the contractor ask to leave 10 percent retainage instead of a bond at $150,000 or less. South Carolina lets the governmental body waive both bonds at $50,000 or less. Mississippi lets the owner elect a lump sum at completion under $25,000. Written up as "bonds required over $X," each of those is wrong twice: bonds do exist below the figure, and the exemption above it is optional rather than automatic.

A bidding threshold. The North Dakota figure in wide circulation came out of the state's competitive bidding statute. The bond requirement is a different section with a different number.

A figure that re-indexes itself. Pennsylvania adjusts its thresholds every single year against a federal construction cost index, which means the amounts printed in the Pennsylvania statute have been stale since 2002. Nebraska re-indexes its state building figure every four years. In states like these the citation is right, the statute is right, and the number is still wrong.

One of two or three numbers. Arizona has no dollar floor for county and city work but a threshold for state agency work. New Hampshire runs $75,000 for state contracts and $125,000 for local ones. North Carolina requires the project total to clear $300,000 and your own contract to clear $50,000, both tests rather than either one.

The bond amount moves too, and it is not always 100 percent of the contract. Alabama's payment bond is at least 50 percent. Illinois and Missouri set no percentage at all and leave the amount to the awarding body. Tennessee's statute says 25 percent, Idaho's 85 percent, Colorado's and Nevada's 50 percent. New Mexico starts at 100 percent and lets the purchasing office cut it to 50.

Citations go stale in a different way. One widely repeated Wyoming citation points at a subsection that was repealed in 2016, and it is not a bond statute at all. It survives online because an older version of the real statute happened to cross-reference it. That is why the table below leads with the statute and the structure instead of a single number, and why every citation in it is a link to the law itself.

Little Miller Act requirements in the 30 states Grit is licensed in

Every citation in the "Read the law" column links straight to the statute so you can read it yourself rather than take our word for it. Where we have read a state's claim and limitations sections, those are linked too.

StateWhat triggers a bondRead the lawClaim noticeDeadline to sue
Alabama$100,000. Performance bond 100%, payment bond at least 50%.Ala. Code § 39-1-145 days' written notice to the surety before you can file.1 year from final settlement, not from your last day.
ArizonaNo dollar floor for county, city and district work. State agency work: over $100,000. Both bonds 100%.A.R.S. § 34-222
§ 34-223 (claims)
§ 41-2574
§ 33-992.01 (20-day)
TWO notices if your contract is with a sub: a 20-day preliminary notice, then 90 days from your last work, sent so you can prove delivery.1 year from your last work, and no suit in the first 90 days.
CaliforniaPayment bond required over $25,000.Cal. Civ. § 9550
§ 9560 (notice)
§ 9558 (limits)
A preliminary notice is the prerequisite. Miss it and you get one cure: notify the surety and the bond principal within 15 days of a recorded notice of completion, or within 75 days of completion if none was recorded. Laborers are exempt.6 months after the stop-payment-notice period closes.
Colorado$50,000 local, county, municipal and school. $150,000 state procurement. Statutory minimum 50%.C.R.S. § 24-105-202
§ 38-26-107 (claims)
File a verified statement with the owner by final settlement. On contracts over $150,000 the owner must publish a final-settlement notice. Watch for it.90 days from the PUBLISHED final settlement date, and you must file a lis pendens to hold the funds.
GeorgiaOver $100,000 for state work. The bond amount ratchets up as the contract amount increases. County and city work is a separate chapter.O.C.G.A. § 13-10-40
§ 13-10-60
§ 13-10-63 (notice)
§ 13-10-65 (limits)
30 days from the notice of commencement filing or your first delivery, whichever is later, if the prime filed one. Only if it did not do you get 90 days. Registered or certified mail or overnight.1 year from completion and the state's acceptance.
Idaho$50,000 or more. Note it is 'equal to or greater than', not 'exceeding'. Statutory amount 85%. Covers rented and leased equipment.Idaho Code § 54-1925
§ 54-1927 (claims)
§ 54-1926 (bond)
90 days from your last work if your contract is with a sub. Registered or certified mail.1 year from your last work. If you are a subcontractor, 1 year from when final payment under your subcontract came due.
IllinoisOver $150,000 until Jan 1, 2029, then over $50,000. IDOT and the Tollway: over $500,000. The awarding body fixes the bond amount, so there is no set percentage.30 ILCS 550/1, 550/2180 days to file a verified claim, plus a copy to the contractor within 10 days. Applies to first-tier subs too.1 year from your last item of work or material.
KansasOver $100,000, in a sum not less than the contract. This is a payment bond statute, not a performance bond.K.S.A. § 60-1111None required by statute. You get a direct right of action.6 months from completion. Tied with Tennessee for the shortest here.
MaineOver $125,000. 'Materials' includes equipment rental.14 M.R.S. § 87190 days from your last work if your contract is with a sub. Material suppliers waiting on final quantity estimates get a separate clock.1 year from your last work, or 1 year from the final quantity estimates for a material supplier whose claim was not yet ascertainable.
MichiganOver $50,000. Amount is not less than 25%, set by the governmental unit.M.C.L. § 129.201
§ 129.207 (notice)
§ 129.209 (limits)
§ 129.203 (amount)
TWO notices: 30 days from your FIRST day of work, then 90 days from your last, and the second goes to the contractor AND the governmental unit.1 year from the owner's final payment to the prime, not from your last day.
MississippiNo threshold. Both bonds at not less than the contract amount. Under $25,000 the owner may elect to pay a lump sum at completion, and only then is no bond required.Miss. Code § 31-5-51
§ 31-5-53 (limits)
90 days, certified mail, return receipt. No notice means no action.Payment bond: 1 year from your last work. Performance bond: 1 year from the owner's final payment, or from abandonment or termination if earlier.
MissouriOver $50,000. The public entity fixes the amount, so there is no set percentage. The bond also covers insurance premiums.Mo. Rev. Stat. § 107.170Suppliers below the first tier get nothing without 90 days' notice.The bond statute sets none. It falls to the state's general statute of limitations.
MontanaWaivable below $50,000 for state and local work and below $7,500 for school districts. That is a waiver power, not a hard floor.MCA § 18-2-201
§ 18-2-204 (filing)
§ 18-2-206 (notice)
§ 18-2-206 (notice)
TWO notices: 30 days from your FIRST delivery in the exact form the statute prints, AND a claim filed with the public body within 90 days of the owner's acceptance. A supplier to a sub owes both.The bond statute sets none. It falls to the state's general statute of limitations.
NebraskaPayment bond: no general floor. Exempt only at $15,000 or less state, $10,000 or less local. The $100,000 state building figure re-indexes every four years.Neb. Rev. Stat. § 52-118
§ 52-118.01 (notice)
§ 72-803
Four months from your last work, not 90 days, if your contract is with a sub.The bond statute sets none. It falls to the state's general statute of limitations.
NevadaOver $100,000. Statutory amount 50%.N.R.S. ch. 33930 days from your FIRST day of work, not your last, if you have no contract with the prime.1 year from your last labor or materials.
New Hampshire$75,000 state contracts, $125,000 local. Security at least 100%. Below either figure the owner may still require a bond.N.H. Rev. Stat. § 447:16
§ 447:17 (notice)
§ 447:18 (suit)
File a claim within 90 days after the owner completes and accepts the project. Where you file depends on who let the work.1 year from the day YOU file your claim, not from completion. Superior Court for the county where the work was principally performed.
New MexicoOver $25,000, both bonds 100%. The purchasing authority may cut either one to as low as 50% before it solicits.NMSA 1978, § 13-4-18
§ 13-4-19 (claims)
90 days if you have no direct contract with the contractor.1 year from the date of final settlement, which the OBLIGEE sets. You can pin that date down by requesting a certified statement of settlement.
North CarolinaTwo tests, both must be met: the project total must exceed $300,000 ($500,000 for state agencies and UNC) AND your own contract must exceed $50,000. Both bonds 100%.N.C.G.S. § 44A-26
§ 44A-27 (notice)
§ 44A-28 (limits)
120 days, certified mail. The federal act gives 90.The LONGER of 1 year from your last work or 1 year from final settlement with the contractor.
North DakotaOver $250,000, bond at least equal to the contract price. Do not use the state's bidding threshold for this.N.D.C.C. ch. 48-01.290 days, registered mail, if your contract is with a subcontractor.1 year after completion and acceptance.
OhioNo dollar threshold at all. Any public improvement contract.O.R.C. § 153.54
§ 153.56 (notice)
A 90-day sworn statement to the sureties from EVERY claimant. A separate notice of furnishing only if your work exceeds $30,000 AND you are not direct with the prime. Serve that one late and your recovery is capped at the last 21 days.60 days after notice to the sureties, within 1 year of acceptance.
OklahomaOver $100,000, bond not less than the full contract. Reaches private buildings built on public land, and covers equipment rental and repair parts.Okla. Stat. tit. 61 § 1
§ 2 (claims)
90 days from your last work, to the contractor AND the surety, if your contract is with a sub of any tier.1 year from your last work, but 2 years if you filed a claim inside the first year.
OregonOver $100,000. Over $50,000 for highways, bridges and other transportation work.O.R.S. § 279C.380
§ 279C.605 (notice)
§ 279C.610 (limits)
180 days from your last work, to the contractor AND the agency. Required even if you contracted directly with the prime. 200 days for employee benefit fund claims.2 years from your last work. The longest window here.
PennsylvaniaThree bands: nothing, then performance security of at least 50%, then 100% performance and payment. The dollar figures are re-indexed EVERY YEAR, so the amounts printed in the statute are long out of date. Call us for the current threshold.62 Pa. C.S. § 903
42 Pa. C.S. § 5523
90 days, registered mail, if your contract is with a subcontractor.1 year, but the deadline is in the Judiciary title rather than the bond chapter, so it is easy to miss.
South CarolinaNo threshold. Both bonds 100% of the contract price excluding operation, maintenance and finance costs. At $50,000 or less the body may waive them. Bid security is separate, over $100,000.S.C. Code § 11-35-303090 days. A separate early notice of furnishing removes the cap on what a remote claimant can recover.1 year from your last furnishing.
TennesseeOver $100,000. The act expressly does not apply at $100,000 or less. Statutory amount 25%.Tenn. Code § 12-4-201
§ 12-4-205 (notice)
§ 12-4-206 (limits)
90 days after the PROJECT is completed, not after your last day, and it has to be itemized. Certified mail, return receipt.6 months from completion of the work or from your furnishing. Tied with Kansas for the shortest here.
TexasPerformance over $100,000. Payment over $25,000 for most entities, but over $50,000 if the owner is a municipality or a joint board. Both in the amount of the contract.Tex. Gov't § 2253.021
§ 2253.041 (notice)
§ 2253.078 (limits)
A rolling MONTHLY notice: by the 15th of the third month after each month you worked, to the prime AND the surety, with a sworn statement of account. With no contract with the prime you owe it a second notice by the 15th of the SECOND month. Certified or registered mail.Performance: 1 year from final completion. Payment: 1 year from the date you mailed your notice, and no suit until day 61.
UtahNo statutory floor. Rules set the working number at $50,000 or $100,000 depending on which agency lets the work. Since May 6, 2026, DFCM is not required to bond the projects it administers.Utah § 63G-6a-1103No preliminary notice. Your claim accrues once you are 90 days unpaid.1 year from your last day of work or supply.
VirginiaOver $500,000. Over $350,000 for transportation. The highest general threshold in the country, but the owner can still require a bond below it.Va. Code § 2.2-4337
§ 2.2-4341 (claims)
90 days from your last work if your contract is with a sub. Claims for retainage are exempt from that limit.1 year from your last work. A waiver of your right to sue is VOID unless you signed it AFTER doing the work.
WashingtonNo threshold. Bonds are required on public work generally. At $150,000 or less the contractor may ask to leave 10% retainage instead, and the owner may agree.R.C.W. § 39.08.010
§ 39.08.030 (notice)
§ 39.08.065 (10-day)
TWO notices, both absolute bars: 10 days from your FIRST delivery if you supply a sub, AND 30 days after the OWNER accepts the work, filed with the public body. The 10-day one is the shortest notice in this table.The bond statute sets none. It falls to the state's general statute of limitations. In Washington the two notices are what actually decide the claim.
WyomingOver $150,000, bond not less than 100%. At $150,000 or less the owner may accept another approved form of guarantee and set the amount.Wyo. Stat. § 16-6-112
§ 16-6-113 (claims)
§ 16-6-121 (60-day)
60 days from when you FIRST furnish, to the general contractor, on contracts over $150,000. Miss it and you WAIVE your bond protection, provided the contractor posted the required site sign. You must also notify the obligee when you file, and proceeds are shared PRO RATA.1 year from the owner's final completion determination.

Confirm every figure here against the state before you rely on it.

Everything in this table is subject to verification against the individual state's own current statutes and administrative rules, and against the solicitation for the job you are bidding. We read each state's statutes directly in September 2026 and we link every one of them above so you can check our work rather than take our word for it. That is the point of the citation column.

A figure can be correct today and wrong later. Statutes get amended. Several of these dollar amounts re-index themselves on their own schedule, so the number printed in the statute is not always the number in force. Tier rules change which notice applies to you. And a county, city, school district or transit authority can layer its own requirements on top of the state minimum, which is why the solicitation governs the job in front of you no matter what any summary chart says.

This table is general information for contractors, not legal advice, not a legal opinion, and not a coverage or bonding commitment. If a bid, a bond decision or a claim deadline is riding on one of these numbers, call the Grit team at (801) 505-5500 and we will confirm it against the current statute with you before you act on it.

The deadline that catches people is the one that starts early

The threshold tells you whether you need a bond to bid. The notice and suit deadlines decide whether you actually collect. Almost every contractor we talk to carries the same mental model, borrowed from the federal Miller Act: ninety days from my last day on the job. In a third of these states that model will lose the claim, because the clock does not start when you finish.

Seven states start it when you show up, and Washington gives you ten days. If you supply a subcontractor on Washington public work you have to notify the contractor within 10 days of your first delivery, and the statute says flatly that no suit against the contractor or the bond can be maintained without it. That is the shortest notice in this table by a wide margin. Montana wants notice within 30 days of first delivery, in the exact form the statute prints, and says plainly that "any other type of actual or constructive notice is not sufficient." Michigan wants one within 30 days of your first day of work, and then a second within 90 days of your last, sent to the contractor and the governmental unit both. Nevada gives 30 days from first furnishing. Arizona wants a 20-day preliminary notice before the 90-day one. Ohio wants a sworn statement to the sureties within 90 days from everyone, and a separate notice of furnishing on top of that once your work passes $30,000 and you are not contracting directly with the prime. Wyoming wants notice to the general contractor within 60 days of your first delivery on any job over $150,000, and the penalty for missing it is not a delay, it is losing the bond. In every one of those states a contractor who waits until the job is over has already lost.

Four states start it when the OWNER acts, not when you do. Washington gives 30 days from the owner's formal acceptance of the work, filed with the public body, and without it you have no right of action on the bond at all. Montana gives 90 days from acceptance, also filed with the public body. Tennessee gives 90 days from completion of the public work, itemized. New Hampshire gives 90 days from completion and acceptance, filed with the Secretary of State, the DOT, Administrative Services or a superior court clerk depending on who let the job. Colorado gives 90 days from a final-settlement date the owner has to publish in a newspaper. If you finished your scope eight months before the project did, you are waiting on somebody else's paperwork to start your clock, and you have to be watching for it.

Washington and Montana are in both groups. On either one, a supplier to a subcontractor owes an early notice off its own first delivery and a later filing off the owner's acceptance. Miss either and the claim is gone.

Texas asks every month. Texas is alone here. You mail the prime and the surety a notice by the 15th day of the third month after each month you worked, with a sworn statement of account. Not once at the end. Every month.

The outer deadlines swing just as wide. Kansas and Tennessee both give six months, the shortest here, and Kansas asks for no notice at all along the way. Colorado gives 90 days from a published date. Oregon gives two years, the longest, but demands a notice within 180 days from every claimant, even one that contracted directly with the prime. Oklahoma gives one year, or two if you filed a claim inside the first. North Carolina gives whichever of two one-year clocks runs longer. Texas runs its payment-bond year from the date you mailed your own notice.

And in four states the bond statute sets no deadline to sue at all. Missouri, Montana, Nebraska and Washington leave it to the general statute of limitations, which depends on how the claim is characterized. That is not a licence to relax. In Washington the notices are absolute bars, so the claim is usually decided long before any limitations question arises.

Two provisions worth knowing because they work in your favor. Virginia voids a waiver of your right to sue on the payment bond unless you signed it after the work was done, so the waiver buried in the subcontract you signed up front does not bind you there. South Carolina lets an early notice of furnishing raise your ceiling, because a remote claimant's recovery is otherwise capped at whatever the bonded contractor still owes the party you supplied. And one that works against you: Wyoming shares the bond out pro rata among everyone in the action, so being slow means splitting rather than recovering in full.

Tier coverage is not uniform either. New Mexico case law reaches third-tier suppliers. Mississippi's statute stops at the second tier by its own terms. Oklahoma reaches a sub of any tier. The federal Miller Act stops at the second tier.

How to handle it if you bid in more than one state

Check the actual solicitation first. Public owners state their bond requirements in the bid documents, and that language governs the job in front of you regardless of what a summary chart says.

Then confirm the claim deadlines for that state before you need them, not after. The bonding threshold tells you whether you need a bond to bid. The notice and suit deadlines are what protect the money once you're on site, and those are the ones contractors discover too late.

Grit is licensed in 30 states and writes surety nationally. We handle the federal Miller Act jobs and the state Little Miller Act jobs, and we tell contractors which rules apply to the specific project they're bidding. If you are bidding public work in a state you have not worked before, call us at (801) 505-5500 before you sign and we will walk the thresholds and the deadlines with you.

 See contractor bond requirements by state

 How the Miller Act Affects Your Bonding Strategy

If you're a contractor who wants to compete for federal work - or state and local government work under a Little Miller Act - bonding isn't optional. It's a prerequisite. And the contractors who treat bonding as a strategic asset rather than an administrative hurdle are the ones who grow their federal project portfolios most successfully.

Building a bond program before you need it is the single most important step. Contractors who wait until they find a federal project to bid and then scramble to get bonded often miss deadlines, pay higher premiums, or get declined because their financials aren't organized. Contractors who have an established surety relationship, pre-approved bonding capacity, and current financial documentation on file can move on opportunities quickly - often getting a bid bond issued the same day.

Strengthening your financial profile directly increases your ability to compete for federal work. Every dollar of working capital, every point on your credit score, and every successfully completed bonded project builds the capacity that allows your surety to back larger bonds. The Miller Act requirement isn't just a hurdle - it's a market filter that keeps unqualified contractors from competing for the work. If you're bonded, you're in a smaller, more qualified competitive pool.

 How Contractors Qualify for Bonds

 Contractor Bond Programs

 Increase Your Bonding Capacity

 Contractor Bond Readiness Review 

The Miller Act requires both a performance bond and a payment bond on covered federal jobs. For how the two differ, see performance bond vs payment bond.

 Ready to Bid Federal Work? 

 If you're looking to compete for federal construction projects and need to get bonded - or you already have a bond program and want to ensure it supports your federal project goals - our team can help.

 Questions about Miller Act bonding requirements? Call us at (801) 505-5500 

Get your bond program federal-ready.

A short program review shows you where your bonding capacity stands and what it takes to qualify for the federal jobs you want to bid.

Request a Bond Program Review

Bidding now and need a bond fast? Same-day attention: (801) 505-5500.